West Evansville, April 2025

West Evansville, April 2025

Location, under Lloyd Expressway, bore extended 120' with grade critical for drainage. Progress was challenging due to unexpected sandstone conditions.

Jeffersonville, March 2025

Jeffersonville, March 2025

Bored 183' beneath wetlands with line and grade critical for gravity sewer installation. Precision was essential due to environmental sensitivity and elevation requirements.

Taylorsville, March 2025

Taylorsville, March 2025

 Bored 210' beneath U.S. HWY 31 through sand and gravel soil conditions. Grade was critical with tight tolerances required around existing utilities, demanding precision and control throughout the operation.

Evansville, February 2025

Evansville, February 2025

 Location: Under Lloyd Expressway — 191' bore with grade critical for drainage. Adverse weather, including winter storms and flooding, combined with unstable backstop soil in the ditch line, created significant challenges.

Evansville, December 2024

Evansville, December 2024

Location, Bore under Lloyd Expressway at 116' was critical due to grade requirements for proper drainage. Winter weather and flooding conditions posed significant challenges, impacting accessibility and progress.

Martinsville, November 2024

Martinsville, November 2024

Bored beneath Highway 39 with grade critical for gravity sewer installation, requiring precise alignment to connect seamlessly to the existing line.

Bargersville, November 2024

Bargersville, November 2024

Bored 130' beneath railway with line and grade critical for water line installation. Tight tolerances required to avoid existing utilities, compounded by bitter cold temperatures during execution.